According to a press release from Brighton and Hove City Council, structural testing has confirmed that much of the original cast iron from Madeira Terrace can be repaired and reused, strengthening the heritage-first approach to restoring the seafront landmark. This will be BrightonBeach365’s last (and very wet) report on the famed but troubled arches - see Likely delays to arches work and Madeira Terrace restoration - hurrah!.
Restoration work began on site in November 2024 and is one of the most technically complex engineering projects undertaken on the seafront. A central aim is to repair rather than replace as much of the historic fabric as possible, including the cast iron structure, retained soil and the terrace’s retaining wall, in order to preserve authenticity and limit environmental impact.
Earlier this year, sections of cast iron removed during the first phase of works were sent to a specialist foundry for testing. An initial round of tests proved inconclusive, requiring further analysis. The latest results now confirm that the original structural cast iron can be successfully repaired and reused. Although the testing programme took longer than planned, the outcome has been welcomed by both the council and the Seafront Development Board, the independent body advising on the wider revitalisation of the seafront.
The findings mean that much of the century-old cast iron can be reinstated during the opening phase of restoration. The environmental savings are substantial: producing new cast iron typically generates around eight tonnes of CO₂ per tonne, while repair is expected to produce less than an eighth of that. Across the full structure, the difference is equivalent to the annual carbon footprint of powering more than 2,000 UK homes.
Alongside the testing results, visible progress is now expected on site. The first sections of steelwork for a new fully accessible lift have arrived, forming part of a new route from Marine Parade down to Madeira Drive. Most of the lift steels are due to be delivered by Christmas, allowing residents to see the structure taking shape. The lift is intended to open as part of the first phase of restoration, improving access to the seafront and to businesses along Madeira Drive.Councillor Jacob Taylor said the project required patience because of its technical complexity and the age of the structure, but emphasised that funders and the council were committed to restoring rather than replacing wherever possible. Lord Bassam, chair of the Seafront Development Board, said the confirmation that the cast iron could be reused was crucial and added that the arrival of the lift steels marked an important moment in building momentum on site.